A77 Kirkoswald | Third Party Works

A77 Kirkoswald | Third Party Works

Scheme Summary

Scheduled:
24 April to 29 May 2023
Summary:
Third Party Works

A77 Kirkoswald @ Croftengee Bridge approximately 840m south of Kirkoswald 

There will be Temporary Traffic Signals deployed at the above location to facilitate an integral part of the planned enabling works for Kirk Hill Wind Farm. 

These works are required to form a new turning area for the delivery of the larger turbine components to access site from the A77. 

The works are due to start from Monday the 24th of April and be completed within 5 weeks. 

We apologise for any inconvenience caused.  

Site Contact: 

Richard Grant 

Knights Brown Construction Ltd 

07879 812 143 

Richard.grant@knightsbrown.co.uk